Water main installation continued this week and testing on the first section of water main began.

 

Work Completed This Week

  • Water main was installed past McLaughlin where a temporary cap was installed. Pressure testing of the main from Apple to McLaughlin was completed. Currently the main is being disinfected and tested.
  • Stripped topsoil south of McLaughlin.
  • Started installing water main south of McLaughlin.

 

Anticipated Work Next Week

  • Continue installing water main south of McLaughlin.
  • Assuming passing tests of the water main over the weekend the portion from Apple to McLaughlin will be connected to the existing main on Apple. This will require a brief shutdown of water for residents on East Street. This connection is currently scheduled for Tuesday October 10 starting at 9 AM.
  • Installation of water services from Apple to McLaughlin may begin.