Progress on Jericho Avenue this week included final grading and HMA paving from Kroes to just north of Peter Creek Drive. They also adjusted the fire hydrants to finish grade and began working on restoration areas.
Next week, crews will be working on cleaning up the topsoil and staging areas from this portion of the pathway, ahead of a tentative top course paving date of next Friday.