This Week:
  • 12-inch water main continued along Algoma Avenue and is installed up to the south side of 11 Mile Road.
  • Water services on the west side of Algoma Avenue (between 10 Mile & 11 Mile Roads) were completed.
  • 8-inch water main installation began along Algoma Avenue north of 11 Mile Road.
  • Paving of the right-hand turn lane at 10 Mile Road and two water main crossing locations was completed.
  • One lane of traffic was maintained on Algoma Avenue with flaggers.

 

Next Week:
  • 12-inch water main construction along Algoma Avenue will be completed and 12-inch water main construction will begin along 11 Mile Road pending pipe delivery.
  • 8-inch water main construction along Algoma Avenue will be completed north of 11 Mile Road.
  • 8-inch water main construction may begin on Winding Ridge Trail pending the deliver of 12-inch water main.
  • One lane of traffic will be maintained on Algoma Avenue with flaggers, expect delays.

 

Please contact any project representative if you have questions or concerns.