This week:

  • Dean’s completed water main installation along Packer Drive up to Van Dam Drive.
  • Dean’s worked with the Plainfield Water Department to pressure test and disinfect the newly installed section of water main.
  • Dean’s worked on completing lawn restoration from the beginning of the project up to the White Pine Trail.


Next week:

  • Dean’s will complete water service installation on Packer Drive.
  • Dean’s will install water main on Van Dam Drive and connect to the water main that Wyoming Excavators installed earlier this summer.


Please contact any project representative to the left if you have questions or concerns.