This week:

  • Brewer Avenue is closed to thru traffic. This closure is expected to last through October while the water main and water services are installed along Brewer Avenue and for the culvert replacement at the stream crossing Brewer Avenue.
  • Tree clearing was completed along Brewer Avenue and in the private water main easements between 7 Mile Road and Bittersweet Drive.
  • Dykema started water main construction on Brewer Avenue. Weather permitting, water main construction will be completed today.
  • The Plainfield Water Department installed water services from the existing water main in Brewer into three houses.

Next week:

  • Dykema will begin to install water main on Butternut Drive and Bittersweet Drive.


Please contact any project representative below if you have questions or concerns.