Progress Report
Schippers Excavating has completed water main installation in Wallingford Drive. See status update map above. Water service installation will take place next week after the new water main has been tested. The only water main work that remains to be completed are the water main tie-ins to the existing water main in 6 Mile Road and Brookgate Drive.
Schippers has begun road work on Biddeford Drive and Biddeford Court. The base course of asphalt is tentatively scheduled to take place next Tuesday or Wednesday.
Schippers will coordinate with residents to ensure access throughout the day and will be coordinating with Comstock Park Public Schools to ensure that bus traffic is maintained.
What to Expect Next Week (October 12 – 17)
- Water main testing and water service installation along Wallingford Drive.
- Road work on Biddeford Drive and Biddeford Court. Paving tentatively scheduled for either October 13 or 14.
Projected Timeline
- Mid-October
- Finish water services along Biddeford Drive and Court; complete water main tie-ins at the ends of Biddeford Drive; begin installing new water services along Wallingford Drive
- Mid-October
- Begin road reconstruction
- Late-October
- Project Completion