Work Completed this Past Week
- The new water main was connected to the existing water main system at the south end of Mears and at Country Club Road
- Storm drainage system mainline system was completed
- Several water service lines were replaced throughout the project between the main and the home
- If your water service is already copper or plastic, it will be reconnected to the new water main and not replaced
Work Anticipated Week of September 4, 2023 (Labor Day)
- No work on Monday, September 4, 2023
- Complete remaining water service replacements
- Water main connection at Pinecrest Road – Tentatively scheduled for Tuesday, September 5, 2023
- Water main connections at Tulgeywood Lane and Sunset Dr – Tentatively scheduled for Wednesday, September 6, 2023
- Possible final water main connection at Benston if weather and time allows
- Install drainage catch basins and connect to storm drain system
Work Anticipated Week of September 11, 2023
- Complete any portions of water main not complete
- Complete any portions of storm drainage system not complete
- Begin cutting the road grade to prepare for road base gravel installation
Note about water service replacements: It is normal for the water to be cloudy or rusty immediately after replacement. If it is cloudy, this is most likely due to air trapped in the water. Let the water set and if it clears up, it is just air and the water will clear up in a few days. If it is rusty or discolored, run the cold water in a bath tub or other faucet that doesn’t have an aerator (screen) in the spigot. Run the water until it is clear. Remove and clean any aerators in faucet spigots. This may take an hour to clear.