Here is a brief update for the improvements to Glenside Boulevard between Broadway Avenue (Garrison) and Sherman Boulevard. A considerable amount of work was accomplished again this week throughout the job site.
Work Completed this Past Week:
- Some features of the old industrial building south of WESCO were removed to accommodate the new bike path
- Road gravel base was placed for the road and the bike path north of the railroad tracks
Work Anticipated Week of September 4, 2023 (Labor Day)
- No work will take place on Labor Day
- Continued delivery and placement of road base gravel and preparations for concrete curb and gutter installation
- Interior inspection of the storm drainage system will be completed
Work Anticipated Week of September 11, 2023
- Concrete curb and gutter is tentatively scheduled for installation
- Concrete sidewalk will be replaced in sections on the east side
Construction will still remain on schedule for being completed in September 2023. However, light poles will be delivered in the middle of October. To accomplish the installation of the electrical and lighting safely, the final course of asphalt may be held until late October until the lighting is fully installed so the final road surface is not disturbed.