Progress Report

This Week
  • Schippers was on site middle of the week to address curb stop box issues that the Water Department had flagged.
  • Schippers also completed some other outstanding items in the Bonneville Drive area.
Week of September 13
  • Black Gold will be on site to place the base course of asphalt on driveways in the Bonneville Drive area September 15th.
Week of September 20
  • Black Gold will be on site to place the top course of asphalt on the road and driveways in the Bonneville Drive area September 23rd and 24th.
  • Schippers Excavating will begin water service work along Plainfield Avenue.

 

All of the above dates are tentative and may change depending on weather.

 

What to Expect/Project Timeline

September
  • Water Service conversions along Plainfield Avenue
  • Final paving, restoration, and project clean up