Progress Report:

Progress continues on the direction drill under Macatawa River. Gabe’s has completed the pilot drill under the river and prepared to start the reaming process. Reaming began Thursday (September 12) and is expected to continue into October.Traffic Control/Access: River Hills Drive & Scotts Drive traffic control was improved this week now that work has scaled up in this area with the pilot drill complete. Access through the intersection will remain open for local residents and the Soccer Spot from River Hills Drive (north of Scotts Drive) and Scotts Drive (west of River Hills Drive).