Work completed/in progress:
- Trenchless casing beneath Peterson installed.
- Approximately 600′ of force main installed within Colby Street.
Anticipated work activities for the coming week:
- Construction pit and install trenchless casing beneath Whitehall Road.
- Continue pipe installation within Colby Street, progressing east toward Whitehall Road.