This week, crews focused on continuing construction along Jericho Avenue. The crew from 28 Specialties has finished placing block for all of the large block retaining walls! They will be back early next week to complete the final construction processes and clean up. In the meantime, the earthwork crews will be working to finalize the pathway grading and prepare for pavement by the end of next week.

Next week, the crews plan to remove existing surface on all driveways south of Peter Creek Drive and prepare gravel/asphalt driveways for pathway pavement. Al’s Excavating will also begin working on the storm sewer construction north of the Rogue River. They will start on the south end and construct storm sewer north to the existing enclosed sewer near the White Pine Trail.