Work completed/in progress from the last update:

  • Lakewood/River intersection restored and opened to traffic.
  • Jack and bore beneath CSX Railroad completed and pipe installed.
  • Holland Township main line 16″ water main complete.
  • Holland Township water service work begins.
  • Completed storm sewer installation between Aniline and Division for road reconstruct project.
  • Continued road construction of Lakewood between Aniline and Division, including some curb and gutter installation.
 

Anticipated activities for the upcoming week include:

  • Prepare jack and bore pit for Douglas Ave crossing.
  • Continue road building between Aniline and Division.
  • Continue water service installation and perform several 16″ water main tie-ins, including the tie-in to Holland Township’s elevated storage tank.
  • Continue transmission main installation.