Progress Report

This week:
  • Dean’s completed more bank restoration along the river crossing.
  • Dean’s continued to install water main along Packer Drive up to the White Pine Trail Crossing.
Next week:
  • Dean’s will work on installing some water services along Packer Drive on Monday and Tuesday.
  • The White Pine Trail will be closed to trail users on Wednesday, September 22, at the Packer Drive bridge to install water main across the trail. The trail will be opened again to trail users on Thursday.
  • Dean’s will continue water main installation along Packer Drive heading towards Van Dam Drive.

 

What to Expect

September
  • Water main construction along Packer Drive up to Van Dam Drive
  • White Pine Trail crossing
  • Water main construction along Van Dam Drive
Long Term

Water main and water services along Packer Drive and Van Dam Drive will be installed in 2021. Water main and water services along northern side streets and private drives off of Packer Drive will be installed in the spring of 2022.

 

Important Information

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.

Only those houses along Packer Drive (including the two gravel drive easements south of Rogue Hill Court) and Van Dam Drive will receive a water service as part of the 2021 construction and will be required to connect to it this year. Water main and services on Rogue Hill Court, Rogue Hollow Court, and Packer Woods Drive will be constructed next year with connection required for these houses in the spring of 2022.

 

Project Timeline

  • September
    • Water main construction crossing the White Pine Trail and water service installation along Packer Drive
  • Late September – Mid-October
    • Water main construction and water service installation along Van Dam Drive
  • October
    • Packer Drive road reconstruction
  • Late October
    • Water main construction along private drive easement just south of Rogue Hill Court
  • April 2022
    • Water main construction along Packer Woods Drive
  • May 2022
    • Water main construction along Rogue Hollow Drive and Rogue Hill Drive