Progress Update

Water main installation along the south side of Napier Avenue is complete. Water mains crossing Napier at Berrien, Downing, and Leeds are all complete. The installed water mains have been tested and disinfected.

Water service lines to properties along the south side of Napier Avenue have been installed from Plaza Drive to Sorter Avenue. Water services to properties along the north side of Napier have been installed from Plaza Drive to Leeds.

Surface restoration work along the south side of Napier Avenue has begun—gravel base courses for driveways and top soil for lawn areas. Pavement for driveways will be scheduled in the coming weeks.

 

Up Next

Final water main connections on the north side of Napier at Berrien, Downing, and Leeds are expected as soon as next week. In addition to those connections, there is one remaining stretch of water main to be installed along the north side of Napier from Pipestone to approximately 300 feet west of Pipestone. This last stretch of water main will be under the road in the right hand, westbound traffic lane.

Before installing this last stretch of water main along the north side, we expect the focus for the next week or more will be on surface restoration along the south side of Napier Avenue.

 

Completion Schedule

Completion of the project is currently anticipated to occur by the end of October.