This Week

Elmer’s worked on clearing for the lake overlook at 16th Street and north of NMC, and the fishing/kayak deck at the City park property. Crews also worked on spreading topsoil and working on general restoration a the City Park property.

They also continue to work on the retaining walls just east of NMC.

Specialized equipment arrived this week to set the boardwalk piles next week.

 

Next Week

They will continue to work on the three walls near NMC

Piles should arrive this week and they will move forward setting them for the boardwalk across the cove area on Boardman Lake.