This week saw the Contractor (McCormick Sand) installing water hydrants, new water main valves and some storm sewer.

 

Work Completed This Week (September 14 – 18)

  • McCormick  completed water main improvements at the McConnell Intersection.
  • McCormick  completed a number of water services.
  • McCormick  began storm sewer replacements at Casenelli and McConnell Intersections.

 

Anticipated Work Next Week

  • Water service replacement will continue
  • Storm sewer replacement at Casenelli and Lancaster will be completed.
  • Driveway removals may be started near the end of the week.