This Week:
- CL Trucking & Excavating began water main installation at the intersection of Algoma Avenue and 10 Mile Road.
- Algoma Avenue traffic was maintained with a traffic shift around the work zone.
Next Week:
- CL Trucking & Excavating will continue installing 12-inch water main north along Algoma Avenue.
- Algoma Avenue traffic will be down to one lane at the work zone and maintained with flaggers, expect delays.
Please contact any project representative below if you have questions or concerns.