Note: CSX is planning to close Lakewood between Beeline and River to replace a section of track in Lakewood. The work is anticipated to take one week starting 9/12. Traffic will be detoured via Beeline/James/Division/Ottawa Beach.

Work completed/in progress from the last update:

  • Pavement removal in River between Lakewood and Douglas.
  • Transmission main installed and pressure tested through Lakewood/River intersection and up to McDonalds.
  • Continued with Holland Township 16″ water main installation. Installation complete to just west of Township’s elevated tank.
  • Lakewood/River intersection restoration underway.
  • Continued storm sewer installation between Aniline and Division for road reconstruct project.
  • Installed second groundwater treatment system.

Anticipated activities for the upcoming week include:

  • Complete Lakewood/River intersection restoration and open to traffic by next weekend.
  • Continue transmission main installation.
  • Install additional dewatering as necessary.
  • Continue Holland Township 16″ water main installation.
  • Install storm sewer between Aniline and Division for road reconstruct project.
  • Install third groundwater treatment system and relocate current groundwater treatment system.
  • Jack and Bore contractor (Lowe Construction) is tentatively scheduled to arrive near the end of the week.