This week, the Contractor completed all of the drainage pipe and structures, finishing all of the underground utility work. They continued to spread road gravel base material and prepped for the concrete curb and gutter which is getting installed today on the south side of the road.

Here is what to expect next week, the week of September 23, 2019

The contractor plans to work a full day tomorrow, Saturday, September 21, 2019
More pavement removals at the intersections will be done as well as near Getty. The lane in Getty should be opened next week as well.
They hope to complete all of the concrete curb and gutter on the south side of the road tomorrow, Saturday.
Driveway access will not be available for 3 days to allow for the concrete to cure. Parking is allowed on the street outside of construction hours.
More concrete work will proceed through next week with the north side curb and gutter, sidewalk and driveway approaches.
The road gravel will be graded and prepped for asphalt
The goal at this time is to pave the first course of asphalt next Friday, September 27, 2019
The week of September 30 will be lawn restoration, raising manhole and valve structures in the road, asphalt driveway restoration and hopefully final paving at the end of the week!
The Contractor is still trying to maintain a lane of traffic through the construction zone for access to homes and businesses. However, this lane will not likely continuous through the entire construction site as the road is currently being re-built. Access will be maintained, but you may need to go around the block to get to your home or business. Please remember to access homes south of Broadway from Summit and homes north of Broadway from Sherman.