Progress Report:
- This week Miller Bridge continued work on the pier caps and all have been poured.
- East of the bridge crews are working at clearing topsoil and placing gravel for the pathway.
- West of the bridge the base course of asphalt was paved to 144th Avenue. Also, in this section the concrete curb was poured at 144th Avenue as well.
- Next week crews will pour the ADA ramps at 144th Avenue, and begin restoration, but mainly concentrate their efforts on the path to the east.
- On the bridge they hope to begin setting the beams.