Progress Report:
This past two weeks focused on concrete curbs, sidewalk and drives. At this time all concrete work is completed and the road graded and ready for asphalt!
Upcoming Work:
The first course of pavement will be applied this weekend weather permitting. Next week will focus on spreading topsoil, raising manhole covers and preparing for the final course of pavement.