This Week:
- Concrete work along Miramar between Eldon and Northgate was completed.
- Topsoil restoration continued along Miramar.
Next Week:
- Concrete work will continue along Miramar between Northgate and Plainfield.
- The concrete bike path at Miramar and Airway will also be replaced next week.
- Lawn restoration work along Miramar Avenue will continue.
- Paving of the asphalt patches is tentatively scheduled for next Saturday (9/28).