Last Two Weeks:
- Wyoming completed lawn restoration and cleaned up the project site.
- Asphalt driveways and road patches had the final layer installed.
- Private side water service installation has begun in earnest. Reference the map above which tracks the progress to date.
Remaining Work:
- Wyoming will be back at a later date to address outstanding items, one of which is irrigation systems that still need repairs completed.
- Traffic control devices will be removed from the site.
- Homeowners will continue schedule directly with the General Contractor they selected to install the new water service into the house.
Please contact any project representative if you have questions or concerns.