This week

Brenner Excavating made good progress removing top soil and grading out the route for the trail. Despite the rain, the crews stripped sod and top soil along Kuttshill Drive from Rogue River Avenue to Northedge Drive.

 

Next week

They plan to continue stripping top soil near Brewer Avenue and begin placing sand (if necessary) and gravel base for the trail along Kuttshill Drive.