Progress Report

This week:
  • CL Trucking completed water service installation on Terrie Lynn Drive and Meek Drive between Terrie Lynn and Herrington Avenue.
  • CL Trucking tested the newly installed water main in Meek Drive and Korben Woods Court.
  • CL Trucking connected the newly installed water main to the water main at the intersection of Meek Drive and Terrie Lynn Drive.
  • CL Trucking began concrete curb and driveway restoration along Pine Hill Drive.
Next week:
  • CL Trucking will complete water service installation in the Hamilton Woods neighborhood.
  • CL Trucking will continue driveway restoration throughout the project.

 

What to Expect/Project Timeline

September
  • Water service construction
  • Water main construction on Meek Drive
October
  • Water main construction on Meek Drive
  • Road, driveway, and lawn restoration

 

Important Information

Once the water service stub has been installed out to the public road right-of-way in front of your house, you will receive a letter from our staff on site informing you that your water service is ready for connection. You will have sixty (60) days from the date of the letter to connect to the municipal water system. If you have not already contacted a private water service contractor about installing your free water service, you should do so as soon as possible to ensure you can meet the sixty (60) day connection requirement.