Work completed the past week includes:

  • Approximately 500 feet of 4-inch sanitary sewer installed and air tested.

 

Below is a summary of activities expected for next week (9/28 – 10/03):

  • Complete 48-inch sanitary sewer installation.
  • Install Manhole #10.
  • Commence 36″ sanitary sewer installation in Red Arrow Highway.
  • Begin reconstruction of northbound lane of Red Arrow Highway.

 

48" Sanitary Sewer Installation