This Week:
- It was a less productive week than originally anticipated due to the rain early in the week.
- Concrete work along Miramar between Northgate and Plainfield is wrapping up this week.
- Milbocker continued general project clean up.
Next Week:
- Any remaining concrete work will be completed.
- Milbocker work to will wrap up lawn restoration and outstanding punch list items.
- Paving of the asphalt patches was rescheduled for next Saturday (10/5).
*PHASE 2 CONSTRUCTION UPDATE*
Residents along Audley, Daylor, and Northgate should have received a letter this week with information about Phase 2 of this project. A preconstruction meeting was held this week Thursday with Montgomery Excavating and more details can now be provided.
Montgomery Excavating intends to start tree clearing for all of Phase 2 on October 4. Trees that will need to be removed for water main construction will be marked on Monday. Water main construction will begin on Audley Drive the week of October 7. Montgomery plans to complete construction on Audley this fall. Construction on Daylor and Northgate is planned for Spring 2025 at this point.