As of this week, the final water main connections along West River Drive are wrapping up . Water services along West River Drive have been switched from the temporary water main back to the newly lined water main. The water main along 4 Mile Road has passed all required testing as of this week.

Next week, the water main connections along 4 Mile Road will be completed. Once the connections have been completed the water services will be switched off of the temporary water main and all temporary water main piping will be removed. Final restoration on the project will take place the week of October 7.