This week, crews from Brenner Excavating have continued stripping topsoil and preparing the pathway corridor for the gravel base along Whitneyville and 66th street.
Next week, surveyors will be onsite to begin staking the pathway on McCords. Crews from Brenner will continue grading the gravel sub base on Whitneyville and 66th and will also begin installing the storm sewer on McCords by the end of next week.