Work Completed this week (9/4 –9/8):
- Installed storm sewer between Surprise and Roy Ave.
- Poured curb between Lamont and Melrose Ave.
- Paved (base/leveling) between Lamont and Melrose Ave.
Work next week (9/11 – 9/15):
- Continue storm sewer install between Roy and Surprise Ave.
- Remove pavement between Bronson and Olmstead.
- Continue Water main install between Surprise and Olmstead.