Water main installation on East Street began this week starting near Apple Avenue and working south.

Work Completed This Week

  • Installed approximately 800 ft of water main from Apple to the south.
  • Finished miscellaneous concrete removals for East Street.

Anticipated Work Next Week

  • Continue installing water main toward McLaughlin. Once water main is up to McLaughlin the Contractor intends to flush, pressure test and start chlorination of that section.
  • During testing, water main installation will continue to the south.