Water main installation on East Street began this week starting near Apple Avenue and working south.
Work Completed This Week
- Installed approximately 800 ft of water main from Apple to the south.
- Finished miscellaneous concrete removals for East Street.
Anticipated Work Next Week
- Continue installing water main toward McLaughlin. Once water main is up to McLaughlin the Contractor intends to flush, pressure test and start chlorination of that section.
- During testing, water main installation will continue to the south.