This Week:
  • Sanitary sewer and lateral replacement continued in Northville Drive.
  • Storm sewer replacement continued in Northville Drive.
  • Sections of sidewalk were replaced on Northville Drive and Leelanau Drive.
  • New gravel was hauled in and road reconstruction continued in preparation for paving next week.

 

Next Week:
Northville (Nippon to 5 Mile)
  • Sanitary sewer and lateral replacement will continue.
  • The final water main tie-in at 5 Mile Road will be completed next Tuesday.
  • Storm sewer replacement will continue.
  • 5 Mile Road eastbound traffic will be shifted to the center turn lane to accommodate water main and sanitary sewer work at the intersection of Northville Drive and 5 Mile Road. This is anticipated to last until Friday (10/7).
Northville (Lakehurst to Nippon)
  • Base course paving is scheduled for next Tuesday.
Leelanau
  • Restoration efforts will continue.

 

Please contact any project representative if you have questions or concerns.