This Week:
- Sanitary sewer and lateral replacement continued in Northville Drive.
- Storm sewer replacement continued in Northville Drive.
- Sections of sidewalk were replaced on Northville Drive and Leelanau Drive.
- New gravel was hauled in and road reconstruction continued in preparation for paving next week.
Next Week:
Northville (Nippon to 5 Mile)
- Sanitary sewer and lateral replacement will continue.
- The final water main tie-in at 5 Mile Road will be completed next Tuesday.
- Storm sewer replacement will continue.
- 5 Mile Road eastbound traffic will be shifted to the center turn lane to accommodate water main and sanitary sewer work at the intersection of Northville Drive and 5 Mile Road. This is anticipated to last until Friday (10/7).
Northville (Lakehurst to Nippon)
- Base course paving is scheduled for next Tuesday.
Leelanau
- Restoration efforts will continue.
Please contact any project representative if you have questions or concerns.