This Week:
- Montgomery continued restoration efforts and general project clean up.
- Water main valve boxes in roads were adjusted in preparation for final paving.
Next Week:
- Montgomery will finish restoration work, including the repairs of damaged irrigation systems, and general project clean up.
- Montgomery will come back in two weeks after final paving is completed to finish lawn restoration along the edges of the new asphalt.
Final Paving:
- Final paving on Green Timbers Drive and in the Cottages on the Rogue neighborhood is tentatively scheduled for October 10. This is weather dependent and subject to change.
Please contact any project representative if you have questions or concerns.