Progress Report

About one-third (1/3) of the homes along the new water main have now connected to the municipal water system. Water service quotation forms have been received for 86% of the houses along House Street. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible in order to meet the 60-day connection requirement.

DeSal is in the process of installing a water main to the Belmont Armory.

 

Road Work Update

 

What To Expect (Week of September 14 (weather pending))