Schippers Excavating has installed new water main in Biddeford Dr. from 6 Mile Road to Westfield Drive. They are averaging an installation rate of about 140 feet of water main per day.

Schippers will not be on site Friday or Monday due to the holiday weekend.

Schippers may have a second crew on-site in the next couple weeks to help install water main.

 

What to Expect Next Week (September 8 – 12)

  • Schippers will be back on site Tuesday, September 8 to resume water main installation.