This week, the Contractor installed drainage pipe and structures except near Huizenga Street. The old water main has been removed from the ground. The road is being cut on the south side and getting ready for base gravel to be installed next week.  Gravel road base material began being delivered to the site and it began to be placed near Getty and Continental.

Here is what to expect next week, the week of September 9, 2019

The Contractor is still trying to maintain a lane of traffic through the construction zone for access to homes and businesses. However, this lane will not likely continuous through the entire construction site as the road is currently being re-built. Access will be maintained, but you may need to go around the block to get to your home or business. Please remember to access homes south of Broadway from Summit and homes north of Broadway from Sherman.