This Week:
- Milbocker completed the water main crossing of Miramar Avenue at Plainfield Avenue.
- Milbocker completed the water main connection at the south end of Northgate Street.
- Milbocker completed the few remaining water service replacements along Miramar.
- Restoration work north of Eldon Street continued.
- Some sidewalk that was poured prior to the thunderstorm last week was removed because the rain damaged the finished surface of the concrete.
- The existing water main in Miramar Avenue north of Eldon Street was abandoned.
Next Week:
- The final water main connection at Plainfield Avenue will be completed on Monday. This will impact a few businesses south of Miramar Avenue. The impacted businesses have been notified of the shutdown by the Plainfield Water Department.
- Concrete work will continue along Miramar Avenue.
- Restoration work along Miramar Avenue will continue.