The horizontal direction drill (HDD) under Macatawa River continues. Progress continues with approximately 500 feet remaining for the pilot drill, with 1,500 feet completed. Preparation on the north side of the bore continues in anticipation of the drilling reaching the intersection of River Hills Dr. & Scotts Drive. Utility verification was completed along River Hills Dr., and the first load of 30-inch HDPE pipe was delivered. Once pilot drilling is complete, Gabe’s will begin the reaming process of the drill.