Note: CSX is planning to close Lakewood between Beeline and River to replace a section of track in Lakewood. The work is anticipated to take one week starting 9/12. Traffic will be detoured via Beeline/James/Division/Ottawa Beach.

Work completed/in progress from the last update:

  • Transmission main installed up to the Railroad in River.
  • Continued with Holland Township 16″ water main installation. Installation complete to eastern limit of replacement work (near Wendy’s)
  • Lakewood/River intersection restoration underway. *Paving is completed. Pavement markings and traffic signal work will be completed tomorrow and intersection will be open to traffic tomorrow*
  • Continued storm sewer installation between Aniline and Division for road reconstruct project.
  • Began road construction of Lakewood between Aniline and Division.
  • Installed third groundwater treatment system and relocated first system.
  • Installed dewatering wells.
  • Lowe Construction arrived on-site and began preparing bore pit for Railroad crossing.
  • Began disinfection of 16″ water main.

Anticipated activities for the upcoming week include:

  • Continue transmission main installation.
  • Install additional dewatering as necessary.
  • Continue Holland Township 16″ water main installation, testing, and start water services.
  • Install storm sewer between Aniline and Division for road reconstruct project.
  • Jack and Bore beneath Railroad.
  • Continue road construction between Aniline and Division.