This Week:
- K&R tested the new water main on Northville between Manitou and 5 Mile.
- K&R completed water service replacement between Nippon and Manitou.
- K&R completed a water main tie-in on the Manitou stub street.
- K&R continued sanitary sewer replacement on Northville between Leelanau and Manitou.
- K&R worked on road reconstruction on Leelanau.
- Concrete sidewalks on Leelanau and Northville continued to be replaced.
Next Week:
Northville (Leelanau to 5 Mile)
- K&R will continue sanitary sewer replacement.
- K&R will complete a water main tie-in and begin water service replacement between Manitou and 5 Mile pending passing disinfection testing this week.
- K&R will complete storm sewer construction between Leelanau and Nippon.
Northville (Lakehurst to Leelanau)
- K&R will continue to work on road reconstruction in preparation for paving later this month.
Leelanau
- K&R will continue to work on road reconstruction in preparation for paving later this month.
Please contact any project representative if you have questions or concerns.