This Week:
- CL Trucking & Excavating continued water main installation along Algoma Avenue and is working their way north.
- CL Trucking & Excavating is filling and pressure testing the first section of new water main today.
- One lane of traffic was maintained on Algoma Avenue with flaggers.
Next Week:
- CL Trucking & Excavating will disinfect the first section of new water main pending a passing pressure test today.
- Pending passing test results, CL Trucking & Excavating will begin to install water services on the first section of new water main.
- CL Trucking & Excavating will continue installing 12-inch water main north along Algoma Avenue.
- One lane of traffic will be maintained on Algoma Avenue with flaggers, expect delays.