This Week:

  • Wyoming continued lawn restoration.
  • Wyoming continued to work on repairing damaged irrigation systems.
  • Concrete driveways and curbs were replaced throughout the project.
  • Asphalt driveways and road patches had the base layer installed on Thursday.

 

Remaining Work:

  • Wyoming will fix all damaged irrigation lines.
  • Wyoming will place topsoil and seed around all driveway edges after the asphalt work has been completed.
  • Wyoming will complete any remaining seeding of disturbed lawn areas. It is very important that you water your new grass to promote good grass growth.
  • Asphalt driveways and road patches will have a final top course of asphalt installed at a later date. The exact date of this work is currently unknown.

 

Please contact any project representative if you have questions or concerns.