This Week:
- K&R installed long side water services on Leelanau. K&R should have all of the short side water services completed tomorrow (Saturday).
- K&R installed 24-inch storm sewer in Northville.
- K&R completed sanitary sewer installation on Northville between Lakehurst and Leelanau.
- K&R began sanitary sewer installation in Leelanau.
- Northville and Leelanau were closed to thru traffic.
Next Week:
- K&R will complete water main tie-ins on Leelanau.
- K&R will continue sanitary sewer lateral replacement in Northville.
- Northville and Leelanau will continue to be closed to thru traffic.