All water services are ready for connection. If you have not already coordinated with a general contractor to get your free water service installed, you must do so as soon as possible to ensure you can meet the sixty (60) day connection requirement. If you have any questions about the process, please call Jeremy Kamp at (616) 432-6709.

 

This Week:

  • Schippers completed water service installation along Brent.
  • Schippers had their concrete subcontractor on site to replace concrete curb and gutter along 10 Mile near Algoma.
  • Schippers continued lawn restoration along Herrington and 10 Mile.

 

Next Week:

  • Schippers will work on concrete driveway restoration.
  • Schippers will finish concrete curb and gutter work along 10 Mile.
  • Schippers will begin preparing asphalt driveways and road patches for paving in early August. A date for paving has not yet been set.
  • General project cleanup.

 

Please contact any project representative if you have questions or concerns.