Today’s construction activities will be concentrated between #988 and #1026 Kinney Ave. Macy Dr. will be closed at Kinney Ave throughout the day. Local traffic seeking to travel through this area should expect delays or seek an alternate route.

Progress along Kinney Avenue continues on!  Here’s a quick update for this week:

Work Completed Last Week

  • Drive approaches and mainline sidewalk on the east side of Kinney Avenue were installed from GVSU Private Drive to Edinboro Street
  • The 30-inch water main was crossed under with 30-inch storm sewer on Wednesday.
  • 30-inch mainline storm sewer will continue to be installed north of Thornwyk Drive.
  • The top course of asphalt on the GVSU Private Drive was placed on Friday and topsoil was installed.

Anticipated Work This Week

  • Continue installing mainline storm sewer from just north of Thornwyk Drive to the north.  Storm sewer is anticipated to be completed before the end of the month.
  • The northbound lane of Kinney Avenue will be milled all the way to the project limits near Leonard Avenue.
  • The roadway will be built up to the aggregate base from Edinboro Street to the north.