Work completed this last week:
- N Court St– The installation of all water main was completed. This section of water main was then pressure tested and passed. Chlorination to occur next week.
- S Court St – The installation of all water main was completed. This section of water main is scheduled to be pressured tested and chlorinated next week.
Anticipated work for this week:
- N Court St – Chlorinate the water main and complete water main tie-ins on Thursday if samples pass. Install the storm sewer at the intersection of N Court/Bellevue.
- S Court St – Pressure test and chlorinate the water main. Install storm sewer at the intersection of S Court/Lake. Complete the tie-ins potentially on Friday.
- Vine St – Start water main installation on Wednesday.