Progress Report:

  • Construction of the north plaza subbase and “paver grate” to support the permeable pavers as well as electrical conduit and uplighting is complete.
  • Four of the 6 plaza trees are planted.

Upcoming Work:

  • The installation of north plaza aggregate base and permeable pavers.
  • Utility work in Bridge Street begins next week. The road will be closed for a short period of time with traffic detoured around the construction.