Work to Date
- Watermain has been placed along Burger between Goodwood and Tuscany.
- Contractor has begun filling the new main in preparation for testing and chlorination.
Work Upcoming
- The Contractor and the City of Grand Rapids will begin the pressure testing and chlorination of the watermain placed along Burger between Goodwood and Tuscany.
- The Contractor anticipates that a second crew will be on site during the week to begin preparations for the Burger Bayou crossing scheduled for the week of April 24th.
The main crew will strip topsoil along Tripoli and Tripoli Ct between Burger and Tuscany and begin placing the new watermain in that location.