Despite activity slowing down during the winter months and a wet spring, CopperRock has continued to push forward at Schmidt Heritage Park:
- Plantings around the common areas continue along with irrigation work near the pickleball area, restroom, and other common areas.
- The Jo-Jo Jogging Trail has been cleared and work is underway with installation of the jogging trail chips and fines.
- Boardwalks crossing from the main fields into the woods along the Jo-Jo Jogging Trail are nearing completion.
- Site sidewalk is being completed.
- Shelters and dugouts are in place.
- Restroom and maintenance building interior work continues.
- Startup of the sprinkling system is anticipated soon with work on final preparations for seeding to follow.
- Fencing continues throughout the site.
- Ballfield material is in place.
- GHCT will be installing the Schmidt Heritage Park sign at the entrance soon.